Engineering runs (ERs) represent a critical yet often underappreciated component of modern biopharmaceutical validation strategies. Defined as non-GMP-scale trials that simulate production processes to identify risks and optimize parameters, Engineering Runs bridge the gap between theoretical process design and manufacturing. Their integration into the ASTM E2500 verification framework creates a powerful synergy – combining Good Engineering Practice (GEP) with Quality Risk Management (QRM) to meet evolving regulatory expectations.
When aligned with ICH Q10’s pharmaceutical quality system (PQS) and the ASTM E2500 lifecycle approach, ERs transform from operational exercises into strategic tools for:
- Design space verification per ICH Q8
- Scale-up risk mitigation during technology transfer
- Preparing for operational stability
- Continuous process verification in commercial manufacturing
ASTM E2500 Framework Primer: The Four Pillars of Modern Verification
ASTM E2500 offers an iterative lifecycle approach to validation:
- Requirements Definition
Subject Matter Experts (SMEs) collaboratively identify critical aspects impacting product quality using QRM tools. This phase emphasizes:- Process understanding over checklist compliance
- Supplier quality systems evaluation
- Risk-based testing prioritization
- Specification & Design
The standard mandates “right-sized” documentation – detailed enough to ensure product quality without unnecessary bureaucracy. - Verification
This phase provides a unified verification approach focusing on:- Critical process parameters (CPPs)
- Worst-case scenario testing
- Leveraging vendor testing data
- Acceptance & Release
Final review incorporates ICH Q10’s management responsibilities, ensuring traceability from initial risk assessments to verification outcomes.
Engineering runs serve as a critical bridge between design verification and formal Process Performance Qualification (PPQ). ERs validate critical aspects of manufacturing systems by confirming:
- Equipment functionality under simulated GMP conditions
- Process parameter boundaries for Critical Process Parameters (CPPs)
- Facility readiness through stress-testing utilities, workflows, and contamination controls
| Demonstration/ Training Run prior to GMP area | Shakedown. Demonstration/Training Run in GMP area | Engineering Run | cGMP Manufacturing | |
| Room and Equipment | ||||
| Room | N/A | IOQ Post-Approval | Released and Active | |
| Process Gas | Generation and Distribution Released Point of use assembly PQ complete | |||
| Process utility | ||||
| Process Equipment | Functionally verified or calibrated as required (commissioned) | IOQ Approved | Full released | |
| Analytical Equipment | Released | |||
| Alarms | N/A | Alarm ranges and plan defined | Alarms qualified | |
| Raw Materials | ||||
| Bill of Materials | RM in progress | Approved | ||
| Suppliers | Approval in Progress | Approved | ||
| Specifications | In Draft | Effective | ||
| Release | Non-GMP Usage decision | Released | ||
| Process Documentation | ||||
| Source Documentation | To be defined in Tech Transfer Plan | Engineering Run Protocol | Tech Transfer closed | |
| Batch Records and product specific Work Instructions | Draft | Reviewed Draft | Approved | |
| Process and Equipment SOPs | N/A | Draft | Effective | |
| Product Labels | N/A | Draft Labels | Approved Labels | |
| QC Testing and Documentation | ||||
| BSC and Personnel Environmental Monitoring | N/A | Effective | ||
| Analytical Methods | Suitable for use | Phase Appropriate Validation | ||
| Stability | N/A | In place | ||
| Certificate of Analysis | N/A | Defined in Engineering Protocol | Effective | |
| Sampling Plan | Draft | Draft use as defined in engineering protocol | Effective | |
| Operations/Execution | ||||
| Operator Training | Observe and perform operations to gain hands on experience with SME observation | Process specific equipment OJT Gown qualifiedBSC OJT Aseptic OJT Material Transfer OJT (All training in eQMS) | Training in Use | |
| Process Lock | As defined in Tech Transfer Plan | 6-week prior to execution | Approved Process Description | |
| Deviations | N/A | N/A | Process – Per Engineering Run protocol FUSE – per SOP | Per SOP |
| Final Disposition | N/A | N/A | Not for Human Use | Per SOP |
| Oversite | PP&D | MS&T | QA on the floor and MS&T as necessary | |